+ | Long-running projects face the challenge that either the process instance used throughout the project lifetime is getting outdated or at best does not benefit from process improvements, | ||
+ | |||
+ | A process is typically divided into phases that have a defined completion gate and time (typically a milestone) and have a chronological order. Therefore those phases are a suitable entity to distinguish process parts that are already completed and need to be stable from process parts that are still executed and therefore should get updated. | ||
+ | |||
+ | //Note: While this guide uses the terminology of freezing phases Stages is not restricted to using phases as freezable elements but almost any kind of element.// | ||
+ | |||
+ | Stages processes are distributed and updated by utilizing the concept of core processes. For preventing process modifications, | ||
+ | |||
+ | To achieve the goal of freezing process parts, the concept of process phases or as general term process modules is needed. A process module is defined by its root element and rules of which dependent and associated elements are also part of the module (e.g. a phase and all its executed activities). | ||
+ | |||
+ | Executing the Phase Freeze for a certain phase will create a new process baseline based on the valid version to save the state of the process at the time of freezing. From those frozen baselines and the working revision, a new merged valid version is created that contains the state of the frozen baselines for elements of frozen phases and the updated working revision for not frozen elements. | ||
+ | |||
+ | There might be process elements that are used in more than one phase, so they might be needed in an older revision for a frozen phase while other unfrozen phases need the up to date revision. These kinds of conflicts are resolved by moving the older frozen revision of shared elements below a new process element folder called " | ||
+ | |||
+ | \\ | ||
+ | Project data like project attributes and files are no longer editable in case the owning process element is part of a frozen phase. Therefore not only the process but also the project state of that phase is frozen. | ||