====== Import processes into MS Project ====== | ====== Import processes into MS Project ====== |
| |
After instantiating a process for a project or program and tailoring it to the requirements, it saves a lot of time to export the project process to planning tools like MS Project. For maximum flexibility, Stages can export the process data via a report to Excel, which can be directly imported into MS Project and other tools. | Planning a project or program should be aligned with the defined process. After instantiating a process and tailoring it to the requirements of a project or program, the process data can be exported to planning tools like MS Project. For maximum flexibility, Stages can export the process data via a report to Excel, which can be directly imported into MS Project and similar planning tools. |
| |
| ===== Set up the MS Project import schema ===== |
| |
| This step only needs to be executed once during the very first import. |
| |
| Data from Excel can be directly imported into MS Project. The information which column holds which attribute can be stored in a MS Project import scheme. You can either create this yourself (see below in [[:72:msproject#run_the_ms_project_import|Run the MS Project import]]) or install a pre-defined scheme. |
| |
| To install the pre-defined scheme into your global MS Project preferences, follow these steps: |
| |
| * Download {{:72:stages-export-template.mpp|this template MS Project plan}} (Do "Left Click > Save link as ...") that contains the scheme |
| * Open this plan in MS Project |
| * Go to ''File > Organizer'' |
| * Go to the ''Schemes'' tab |
| * Select the ''Import from Stages'' scheme on the right side of the screen |
| * Click on ''< < Copy'' |
| |
===== Run the Stages report ===== | ===== Run the Stages report ===== |
Navigate to the workspace and process version you would like to export. | Navigate to the workspace and process version you would like to export. |
| |
The process data can be exported via this report. In a typical Stages instance, this report is already installed as ''Reports > Exports > Project Planning''. | The process data can be exported via the ''Project Planning'' report found here. In a typical Stages instance, this report is already installed as ''Reports > Exports > Project Planning''. |
| |
Select the processes you would like to export via the ''Processes to export'' parameter. You can select multiple processes by holding the CTRL or SHIFT keys during the selection. Then run the report. | {{ :72:msproject-report.png?direct&799x441 }} |
| |
Export the report results to MS Excel via the ''XLSX Export'' menu. | **<font inherit/inherit;;#ffffff;;#e74c3c>(1)</font>** Select the processes you would like to export via the ''Processes to export'' parameter. You can select multiple processes by holding the CTRL or SHIFT keys during the selection. |
===== Set up the MS Project import schema ===== | |
| |
The exported Excel file can be directly imported into MS Project. For MS Project to understand which column holds which data, you need to map the columns from the Excel file to the respective MS Project attributes. You can create this mapping yourself (see below) or save time and use a pre-defined import scheme. | MS Project currently only supports importing one predecessor per task. As activities in Stages might have multiple predecessors, the import of those will result in an import error (which can also be simply ignored). With the ''Use only last predecessor'' option, you can control if all predecessors should be exported or only the last one. |
| |
| <font inherit/inherit;;#ffffff;;#e74c3c>**(2)**</font> Then run the report. If you do not need to see the exported data, this step can also be skipped. |
| |
| <font inherit/inherit;;#ffffff;;#e74c3c>**(3)**</font> Export the report results to MS Excel via the ''XLSX Export'' menu. |
| |
===== Run the MS Project import ===== | ===== Run the MS Project import ===== |
| |
Open MS Project and select "New from Excel Sheet". Switch from the "XML Format" to the "Excel Sheet" filter select the file you generated with the Stages report. | To import the process data into MS Project follow these steps: |
| |
| * Open MS Project and select ''New from Excel Sheet''. |
| * Switch from the "XML Format" to the "Excel Sheet" filter and select the XLSX file you generated with the Stages report. |
| * Select either ''Use Existing Scheme'' if you have already set up the import scheme (see above) or ''New Scheme'' if you want to do the attribute mapping yourself. |
| * Select "Tasks" and "Import with headers" in the import assistant "schema options" page. |
| * Check the import preview. If necessary, adjust the attribute mappings and save the import scheme. |
| * If import errors occur, you can either click "Yes" to ignore all of them or use the ''Use only last predecessor'' option when running the Stages report. |
| |
| As a result, your imported process will show up in MS Project. |
| |
| {{ :72:msproject-result.png?direct&801x365 }} |
| |
| For example, you can see that |
| |
| <font inherit/inherit;;#ffffff;;#e74c3c>**(1)**</font> All process activities are imported as tasks, including their hierarchy and order |
| |
| **<font inherit/inherit;;#ffffff;;#e74c3c>(2)</font>** The default duration is set to 1 day, but it can be also modeled in Stages as an attribute. |
| |
| <font inherit/inherit;;#ffffff;;#e74c3c>**(3)**</font> Predecessors and successors as well as input/output dependencies have been transferred |
| |
Select either "Use Existing Scheme" if you have set up the import scheme (see above) or "New Scheme" if you want to do the attribute mapping yourself. | <font inherit/inherit;;#ffffff;;#e74c3c>**(4)**</font> There is a hyperlink from every task back to Stages |
| |
Select "Tasks" and "Import with titles" in the import assistant "schema options" page. | With this capability, the project managers can start planning the tasks in MS Project and your users can use the hyperlink to directly start working on the activity. It is only once more click to access templates and checklists and even input and output work products, independently where they are stored. |
| |
Check the import preview. | ===== Supported MS Project versions ===== |
| |
Save the import scheme. | The concept of exporting data to Excel and importing it should be rather portable. This procedure has been successfully tested with |
| |
Ignore import errors and click "Yes" to ignore all of them. They show up if your activities have multiple predecessors. | * Microsoft Project 2016 |
| |
Your imported process will show up in MS Project. | It will surely work also with other MS Project versions. Please let us know when you were able to make it work also with other versions or tools, then we will add those to this list. |
| |
| |